Schedule/Timeline of my Portfolio Project!
Hopefully we can follow our schedule and finish everything on time...
Week 1 (1/16-1/23):
- Research different genres 🗸
Week 2 (1/26-2/1):
- Create Timeline/Schedule 🗸
- Decide genre, start analyzing different film openings of decided genre
- Decide on how to include credits
- Start brainstorming ideas/start storyboard
- Try to set location, dates/time, and actors if needed for filming days
Week 3 (2/2-2/8):
- Finish Storyboard
- Set location, date/time, and actors for filming
- Start researching/purchasing/planning mise-en-scene needed
- Research on music/sound effects needed
- Potentially start filming
Week 4 (2/9-2/15):
- Start Filming
- Start editing if done filming
- Start sound/foley if done filming
Week 5 (2/16-2/22):
- Finish Filming for sure
- Finish foley/sound after all filming is done
- Still editing
- Film BTS for blog while filming
Week 6 (2/23-3/1):
- Start CCR #1 research
- Hopefully finish editing
Week 7 (3/2-3/8):
- CCR #2 research
- CCR #3 research
- CCR #4 research
Week 8 (3/9-3/17):
- Finish BEFORE due date (finish on 3/14)
- CCR Posts
- Buffer Week